地下闸室开挖与支护仿真分析
首发时间:2010-03-22
摘要:黄金坪电站泄洪洞中闸室开挖规模较大,结构比较复杂,区域内又有多条断层通过,这些都对围岩稳定产生不利影响。运用FLAC/3D软件,结合自己开发的接口程序,基于弹塑性力学的基本理论,对中闸室开挖全过程进行仿真分析,得到了整个施工过程中围岩的应力、变形和塑性区开展变化规律,在此基础上提出了支护建议,为工程设计提供了依据,也可为同类工程及相关研究做参考。
For information in English, please click here
Simulation analysis on Rock Mass and Supporting Effect
Abstract:The mid-gate chamber of spillway tunnel in GoldPing Hydropower Station has a large excavating scale and a complicated structure, as well as multiple faults in its region. These factors will have an adverse impact on stability of surrounding rock. Using Flac/3D software and our own developed interface program, based on the elastoplastic wall rock theory, we carried out numerical simulation analysis in the process of excavation and obtained the changing regularity of stress、deformation、and plastic zone development of wall rock. And on this basis, we proposed shoring advice to provide evidence for engineering design and as a reference for other related researches.
Keywords: underground chamber 3-D elastic-plastic finite element stability of wall rock support
基金:
论文图表:
引用
No.4093451961012692****
同行评议
共计0人参与
勘误表
地下闸室开挖与支护仿真分析
评论
全部评论0/1000